Construction Line
Registered Contractor
CHAS
Health & Safety accredited
SMAS
worksafe accredited
Contact Us

Nottingham Police HQ

by North Nott's Civils Ltd

Project Details

ClientHilton Bodill
ProjectCar Park
LocationSherwood Lodge, Nottingham
CompletionSeptember 2020

Project Description

A new 18.5 million joint headquaters for the police and fire service have been given a go ahead. In anticipation of this, and the work to go ahead, two temporary new car parks will be constructed by North Notts Civils Ltd.

 

FACTS AND INFORMATION

A shared facility will enable effective joint response to major incidents and it will also enhance our ability to work together, providing flexible facilities that will serve the emergency services for many years to come.

OUR WORK

Site Preparation.

A compound was set up, and harris fencing errected to ensure the safety of all staff on site.

Setting Out and Surveying

Stations where installed on site and a survey was conducted to record existing levels and anticipate any problems before commencement. The to be excavated areas where also investigated using a CAT and Genny to scan the area for any unidentified cables.

Car Park Foundations

CBR tests where carried out and the topsoil stripped and carted offsite. Stone was imported and rolled in layers and then trimmed to temporary finish level. During this process various services where also exposed and diverted.

Kerb Line

After the stone was levelled, the kerb line for the car park was pinned out and the kerbs layed.

Concrete Bases

A number of concrete bases were shuttered and poured to house storage containers on site. An electric charging station was also installed on one of the concrete foundations.

Project Testomonial

Coming Soon

Our Clients

We have worked with numerous main line contractors and and key companies in the construction industry.

Our Stats

0+
Years Experience
0
% Safe Commitment
0+
Completed Projects

CERTIFICATIONS

TESTOMONIALS

  • NNC was ranked excellent across twelve metrics including value engineering, responses to instructions and site safety measures whilst completing esplanade wall refurbishment and groyne installation at South End on Sea.

    John Gallagher
    Volker Fitzpatrick
  • NNC was rated excellent in metrics such as quality service, ability to complete on time, working relationship and project resources whilst completing A1260 bridge refurbishments.

    David Gibson
    Geoffrey Osborne Ltd
  • NNC was rated excellent on metrics such as site safety, standard of workmanship, ability to complete on time and working relationship on completion of the £2m Peterborough Cathedral Square Town Centre regeneration project.

    James Keane
    Geoffrey Osborne Ltd
  • NNC was rated excellent across all twelve metrics including; working relationships, traffic management processes, site safety measures and standard of workmanship on completion of the £800,000 278 carriageway alterations on the A45 Red Route.

    Robert Faulkner
    Geoffrey Osborne Ltd
  • NNC undertook the groundworks package at the Melton Mowbray Cattle Market. Works ranged from deep drainage diversions & RC foundations to precisely setting out of bolt boxes & pennage sleeves to the underside of the groundfloor slab. All works were planned and executed on programme given due consideration to the “live” project environement we were working on. I would not hesitate to use NNC again.

    Oliver Smith
    Morgan Sindall
  • NNC’s were approached directly due to the high profile nature of this project to deliver the groundworks package. From our experience on several previous schemes we knew we could rely on them to deliver this flagship project and work with us to ensure its success. NNC’s ability to perform and function as a key project partner meant that we were able to deliver a scheme which exceeded our clients expectations.

    Jason Fairbrass
    Volkerfitzpatrick
  • NNC worked alongside Kiers to deliver this new HQ and teaching facility for Natural England in a live nature reserve. The project was not without its challenges. Nesting seasons created programme constraints and the main bridge entrance to the project was deemed unsafe to use part way through the build. Through all this NNC continued to go above and beyond to ensure programme, budget and quality consideraions were met at all stages. NNC were a key component of this projects successful delivery.

    Thomas Waldon
    Kiers